[Date Prev][Date Next][Thread Prev][Thread Next][Date Index
][Thread Index
]
BKK Post, March 7, 1998 ENERGY / YA
- Subject: BKK Post, March 7, 1998 ENERGY / YA
- From: burma@xxxxxxxxxx
- Date: Fri, 06 Mar 1998 22:12:00
March 7, 1998
ENERGY / YADANA GAS CONTRACT CHANGE PROPOSED
PTT wants lower price and volume of supply
Economic crisis sees lower demand for gas
Chatrudee Theparat Boonsong Kositchotethana
The Petroleum Authority of Thailand (PTT) will seek to amend the gas
deal with the Yadana gas developing consortium to reduce the agreed
supply volume and price of the offshore Burmese gas.
Specifically, the PTT will seek a 20% cut in the agreed gas tariff from
the base price of US$3 per one million BTU (British thermal units) as
well as a reduction in the gas intake from the average 525 million cubic
feet per day (MMcfd) to 400 MMcfd.
Piti Yimprasert, president of PTT Gas, part of the Petroleum Authority
of Thailand, yesterday pointed to the need to amend the 30-year contract
concluded in 1995.
Lower demand for gas in Thailand and the country's economic crisis are
the reasons behind the PTT's move to seek amendment of the contract.
Protests by environmentalists and non-governmental organisation
activities in Thailand have contributed to problems faced by the PTT,
delaying pipeline work.
The negotiations will be held with the Yadana group consisting of Total
of France, with a 31.24% stake in Yadana; the US energy firm Unocal
Corp, 28.26%; PTT Exploration and Production Plc of Thailand (part of
the PTT), 25.5%; and Burmese state-owned Myanma Oil and Gas Enterprise,
15%. The consortium is investing $1 billion in the scheme.
The PTT is bound to take delivery of Yadana gas in July under the
"take-or-pay" deal.
At least for the time being, it is clear that construction of the first
two units of Ratchaburi power plant will be ready to take the Yadana gas
in July as planned. This may also prompt the PTT to ask for the
consortium to delay the start of gas delivery beyond July, according to
Dr Piti.
He said the pipe-laying contractor, the Thai-German joint venture of
Tasco-Mannessmann, had claimed an additional payment of US$40 million
from the PTT, alleging the agency had failed to make arrangements for it
to complete the work as scheduled. The claim would push the pipeline
project cost beyond 16.5 billion baht.
The Kanchanaburi-Ratchaburi pipeline has faced opposition from
environmentalists and NGOs activities because six km section of the line
will be laid through the fertile forest in Kanchanaburi.
NGO activists have in recent months camped out at the forest to block
the pipe-laying work which is now 6-7% behind schedule.
In another development, Dr Piti said additional gas discovery in the
Yadana field had strengthened the chance for Thailand to increase
natural gas procurement from Burma.
It also boosted the economic viabilities of laying a new onshore gas
pipeline in Thailand, specifically from Ratchaburi to Wang Noi in
Ayutthaya, bringing more Burmese gas to consumers in Thailand.
Dr Piti pointed to this picture as he revealed that gas reserves at
Yadana, about 240 km south of Rangoon in the Gulf of Martaban, had
soared from 5.6 trillion cubic feet (Tcf) to nine Tcf.
But he said the realisation of the proposed gas line from Ratchaburi to
Wang Noi was marred by the budget constraints faced by the PTT. The
economic crisis had forced the government to slash the state oil
investment this year, and the PTT was looking at opportunities to
reverse this.
If that was not possible, the private sector would be given a chance to
invest in the pipeline project to ensure the gas line would come on line
next year as targeted.
------------------------------------------------------------------------